North Susanville WUI Fuels Treatments
North Susanville WUI Fuels Treatments - #103 |
---|
Grantor: CALFIRE |
Awarded*: $2,999,924.32 |
Activities: Agreement signed by LFSC. CEQA cleared. Landowner agreements complete. Biomass 100% complete. Mastication 60% complete. |
Remaining Treatment Funds*: $1,500,125 |
Status: Biomass complete off upper Paiute lane and Summit lane. Mastication completed for spring of 2025. Will return in Fall 2025 or Spring 2026 to finish eagle lake road FB. Under budget, assessing more treatment areas. |
Exp Date: 3/15/2030 |
* Does not include proprietary cost match information