Shingletown Phase 2 Fuelbreaks (SHU)

Shingletown Phase 2 Fuelbreaks (SHU) - #134
Grantor: CALFIRE
Awarded*: $949,473.25
Activities: Signed agreement 1/20/2026. HWY 44 Maintenance deliverables completed on 450 acres. MOU executed for thinning and chipping larger fuel concentrations on HWY 44 fuelbreak.
Remaining Treatment Funds*: $800,000
Status: CEQA complete. Permits completed. Hwy 44 maintenance completed. RFP for mastication closed October 2026. Contracts will be awarded in next few days. MOU work on HWY 44 active.
 Exp Date: 3/15/2029

* Does not include proprietary cost match information